NEC4 was announced in March 2017 and has been available since June 2017. This new edition reflects procurement and project management developments and emerging best practice, with improvements in flexibility, clarity and the ease of administration. It also introduces two new contracts: NEC4 Design, Build and Operate (DBO) and NEC4 Alliance Contract (ALC). | NEC4 was announced in March 2017 and has been available since June 2017. This new edition reflects procurement and project management developments and emerging best practice, with improvements in flexibility, clarity and the ease of administration. It also introduces two new contracts: NEC4 Design, Build and Operate (DBO) and NEC4 Alliance Contract (ALC). | ||
− | = | + | ==Characteristics== |
+ | The NEC is a family of standard contracts, each of which has these characteristics: | ||
+ | |||
+ | * Its use stimulates good management of the relationship between the two parties to the contract and, hence, of the work included in the contract. | ||
+ | * It can be used in a wide variety of commercial situations, for a wide variety of types of work and in any location. | ||
+ | * It is a clear and simple document - using language and a structure which are straightforward and easily understood. | ||
+ | |||
+ | The NEC3 complies fully with the [http://www.ogc.gov.uk/guidance_achieving_excellence_in_construction.asp Achieving Excellence in Construction] (AEC) principles. The Efficiency & Reform Group of The UK Cabinet Office recommends the use of NEC3 by public sector construction procurers on their construction projects. | ||
+ | |||
=Features= | =Features= |
Revision as of 11:40, 16 September 2018
The New Engineering Contract (NEC), or NEC Engineering and Construction Contract, is a formalised system created by the Institution of Civil Engineers that guides the drafting of documents on civil engineering and construction projects for the purpose of obtaining tenders, awarding and administering contracts.[1][2] As such they legally define the responsibilities and duties of Employers (who commission work) and Contractors (who carry out work) in the Works Information. The contract consists of two key parts the Contract Data part one (Data provided by the Employer) and Contract Data part two (Data provided by the Contractor). Several approaches are included making it a family of options. It is used in the UK and internationally in countries including New Zealand, Australia, Hong Kong and South Africa.[3]
There have been four editions, the first in 1993, the second in 1995, the third in 2005 and the most recent in 2017. The NEC3 was launched in 2005 and it was amended in April 2013.
NEC4 was announced in March 2017 and has been available since June 2017. This new edition reflects procurement and project management developments and emerging best practice, with improvements in flexibility, clarity and the ease of administration. It also introduces two new contracts: NEC4 Design, Build and Operate (DBO) and NEC4 Alliance Contract (ALC).
Characteristics
The NEC is a family of standard contracts, each of which has these characteristics:
- Its use stimulates good management of the relationship between the two parties to the contract and, hence, of the work included in the contract.
- It can be used in a wide variety of commercial situations, for a wide variety of types of work and in any location.
- It is a clear and simple document - using language and a structure which are straightforward and easily understood.
The NEC3 complies fully with the Achieving Excellence in Construction (AEC) principles. The Efficiency & Reform Group of The UK Cabinet Office recommends the use of NEC3 by public sector construction procurers on their construction projects.